What a contractor has to do before paying a subcontractor

Verify, deduct on labour only, file by the 19th, statement within 14 days. The sequence a CIS contractor owes HMRC, the four ways it goes wrong, and who carries the cost.

If you pay subcontractors in construction, the Construction Industry Scheme puts four duties on you and the liability for all of them sits on your side of the transaction. Not the subcontractor’s. Yours. That is the thing to understand before the first payment, because every one of the four is administrative, none of them are difficult, and the consequences of skipping one land on the business that skipped it.

Is the work even within CIS

The scheme is about construction operations, not about what a firm calls itself or what trade the person doing the work belongs to. Work on a building, structure or civil engineering works counts — including alterations, repairs, demolition, installation of services, and the site preparation that precedes it. There are exclusions, and they are narrower than people assume: professional services such as architecture, surveying or scaffolding design are generally outside the scheme, while the trades that carry them out on site are inside it.

So the question is not “is this a builder”, it is “is this operation construction”. If it is, and you are a contractor within the scheme, everything below applies to every payment.

The four duties, in the order they happen

1. Verify the subcontractor — before the first payment. Verification tells you which deduction rate applies. You can do it through HMRC’s online service or the CIS helpline, and it needs the subcontractor’s UTR and registration details. Do this at the point you engage them, not when the first invoice arrives, because a payment made before verification is a payment made on a guess.

2. Deduct from the labour element only. Materials are excluded from the deduction, and so is VAT. This single sentence is the source of most CIS disputes, and it is worth being pedantic about: get an invoice with labour and materials on separate lines, and apply the rate to the labour figure. If a subcontractor hands you one “works completed” total, send it back — you are the one who has to justify the number to HMRC.

3. File a monthly return. One return per tax month, covering every subcontractor you paid in it, due by the 19th of the following month. A month with no payments still needs a nil return while you are registered as a contractor. This is the duty most often missed by small firms, because nothing arrives to remind them: no letter, no invoice, no customer waiting. The form is simply due.

4. Give the subcontractor a written statement. Within 14 days of the end of the tax month, showing what was paid, the materials and the deduction. It is a requirement, not a favour, and it is also your own audit trail.

On top of that, keep records — the verification numbers, the returns, the statements and the payments — for the period HMRC specifies. Assume three years after the end of the tax year unless you have checked otherwise, and keep them somewhere you can find them.

What it costs when it goes wrong

The unverified subcontractor. The deduction rate depends on registration and verification. A subcontractor who is not registered has the higher rate deducted from their labour. If you never verified someone who was registered, they carry that higher deduction until the year end, and they will notice. It is their money and your process that lost it.

The deduction you did not make. If you pay gross when you should have deducted, HMRC can recover the missing deduction from you — you are liable for it, and recovering it from the subcontractor afterwards is a separate argument you may not win.

The return you did not file. Late returns attract fixed penalties that escalate with repetition, and persistent failure can affect your own gross payment status. For a firm whose cash flow depends on being paid gross, that is an existential risk dressed up as paperwork.

What to record, per payment

A working record per payment, kept as you go rather than reconstructed:

Field Why
Subcontractor name, UTR, CIS number verification and the return both need them
Verification reference and date proves you checked before paying
Invoice number and date ties the payment to the work
Labour the base for the deduction
Materials, VAT excluded, and the figures that settle a dispute
Rate applied, deduction, net paid the statement, and the return
Tax month how the monthly return is assembled

Fill that in per payment and the monthly return becomes a copy rather than a reconstruction. Leave it until the 18th and it becomes an evening of guesswork with a penalty attached if you get it wrong.

The one-page discipline

The firms that never have a CIS problem are not the ones with a clever system. They are the ones where the same three questions get asked before any money moves: has this operation been verified, does this invoice split labour from materials, and has this month’s return gone in? Everything else is arithmetic.

The rules and the current rates are on GOV.UK — what is the Construction Industry Scheme. This page is general information, not tax advice. The subcontractor’s side of the same transaction — what the deduction should be, and how to spot a statement that does not add up — is in CIS deduction on materials and labour.

Three workbooks come with this page: a verification log that holds the reference and date per subcontractor, a per-payment deduction calculator, and a monthly return preparation sheet with the filing checklist.

General information only, not tax or financial advice. Every guide links to the current GOV.UK page for the rules it applies.